Tuesday, July 27, 2010

Under Cover

After an all-day session of work on Monday, the water line box up the cliff from the lake has been insulated and covered with new plywood. Some repairs remain to be completed, but at least now the cover is completed and the new insulation has been protected (we hope) from rodents by wire mesh installed inside the box.

Since repairs were started 2 months ago, a total of 53.5 volunteer person-hours have been put into this project, not counting some time spent in obtaining materials, cutting up plywood and generally preparing for the work.

During the project, it was discovered that almost all of the main water line was not insulated at all because of the dedicated work of mice and pack-rats and their urge to move the materials in the box around. It was very lucky that the main water line didn't freeze during some of our cold spells during the past couple of winters. In addition, the old plywood and supporting structures were found to be in pretty desperate shape. We have at least started to replace and repair that structure.

Thanks to to several member volunteers from the community for the hours of work spent fixing this structure: Bill J, Dave, Bob C, Gerda, Doug and Hugh, some of whom put in many hours over the past 2 months and especially to the group for spending all of Monday in +30C heat to complete the remaining part of the project in one day. A few hours of work remain to cover some of the last defects in the old box with new treated plywood, but at least now the majority of the repairs are done. Thanks again to the members who helped out on this important project.

No comments:

Post a Comment